Pool pictures for Justin
2006-08-05 - Rogers' Drywall up
2005-12-31 - Foundation and plumbing done
Rogers - Feb 5, 2006 - finishing up tie beam on 1st floor
Jan 4, 2006 - Slab about to be poured
Brady's - tile
Rogers' house - May 12, 2006 - stairwell in - 2nd floor pictures
Brady's - Feb 19, 2006 - tie beam done
Brady's - Jan 26 - Foundation down, block going up
Brady's - Jan 21, 2006 - Slab down
Rogers - Jan 21, 2006 - 1st floor walls going up
Rogers - Jan 8, 2005 - Slab about to be poured
Brady's - Jan 29, 2006 - 1st floor block up
Rogers' house - April 6, 2006 - framing started
Jan 10, 2005 - Foundation complete
March 15, 2006 - Rogers and Brady houses
Rogers - Feb 19, 2006 - tie beam done
June 4, 2006 - Rogers - plumbing done, high voltage done, low voltage WIP
4/16/2006 - Rogers' house - framing done
Rogers - March 11, 2006 - 2nd floor block going up
Brady's house - April 9, 2006 - finishing the roof
June 4, 2006 - Bradys' house - Framing up, plumbing about done
Brady's - Feb 5, 2006 - still working on 1st floor tie beam
Brady's - Jan 10, 2005 - Plumbing inspected
Rogers - Feb 26, 2006 - 1st floor trusses
July 7, 2006 - Rogers' - walls done - waiting for insulation
Brady's - Jan 8, 2006 - Plumbing ready to be inspected
Brady's - March 11, 2006 - 2nd floor block going up
April 23, 2006 - Rogers' - Windows almost in - Framing done
July 1, 2006 - Rogers' house - Stucco outside
Rogers - Jan 26th - Block up on 1st floor
Rogers - Jan 29, 2006 - 1st floor block done